BEACH REPLENSHIMENT UPDATE JUNE 2020

BEACH REPLENISHMENT UPDATE LONG BRANCH JUNE 2020

- The beach replenishment is expected to start with the pumping of sand on Sunday 6/14 or Monday 6/15. 
- The work will start at Plaza Ct. on June 15th and continue south to Sycamore Ave. until June 26th. The dredge will return and pump north off Plaza Ct. on June 27th and will complete  the West End section of the project on July 3rd near Avery Ave. Weather delays could occur and extend the schedule. 
- There will always be a 1000-ft area closed for construction. Where possible, there will be access along the western portion, near the bulkhead for the public to pass from one side of construction to the other. 